Tower 28, Malad East

Lapsed

by Shiv Shakti Builders And Developers · Malad East, Mumbai 400097 · Map

Launched
Aug 20174 yrs 10 mths originally promised
Possession (MahaRERA)
Jun 2023Extended by 1 yrWhat does Lapsed mean?
Concrete structure
55%Mid-construction
Booked
315 of 32198%
Buildings
72.8 acres
MahaRERA complaints
51Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
136
2 BHK
185
Total units
321
Buildings
7
Land
2.8 acres
Phases
1
MahaRERA complaints
51

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation57%
Concrete structure (slabs)55%
Finishes, lifts and services43%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 57%Dec 2025: Excavation 57%Jul 2026: Excavation 57%Dec 2024: Concrete structure (RCC) 55%Dec 2025: Concrete structure (RCC) 55%Jul 2026: Concrete structure (RCC) 55%Dec 2024: Final finishes 43%Dec 2025: Final finishes 43%Jul 2026: Final finishes 43%Excavation 57%Concrete structure (RCC) 55%Final finishes 43%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
57%55%43%315
57%55%43%314
57%55%43%310

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400097

Projects with 150–700 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths5 yrs 10 mths
Possession date extendedBy 1 yr5 of 5
Possession date (MahaRERA)Jun 2023Jul 2024
Concrete structure (RCC)55%100%
Units booked98%88%
MahaRERA complaints (filed by or against the builder)5113

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Tower 28 by Shiv Shakti Builders And Developers is a 321-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in August 2017; its MahaRERA registration has lapsed. 315 units booked out of total 321 units. The concrete structure (RCC) is 55% complete.

Read full summary

Tower 28 is an SRA-sanctioned project by Shiv Shakti Builders And Developers in Malad East, Mumbai 400097, registered with MahaRERA as P51800009511. It was launched in August 2017. It has 321 units in 7 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2023, after an extension of 1 year from the original June 2022. That date has passed and no further extension has been recorded. Construction: excavation 57% complete, structure (RCC) 55% complete, final finishes 43% complete.

315 units booked out of total 321 units (98%).