Green Acres, Malad East
by Nirman Realtors And Developers Ltd · Malad East, Mumbai 400097 · Map
- Launched
- Aug 20178 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked
- 120 of 18067% · 112 in Jul 2026
- Buildings
- 11 acre
- MahaRERA complaints
- 19Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 140
- 2 BHK
- 34
- Other units
- 6
- Total units
- 180
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 19
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 85% | 120 | |
| 100% | 100% | 83% | 112 | |
| 90% | 100% | 0% | 112 | |
| 90% | 33% | 0% | 74 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400097
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 8 yrs 4 mths | 3 yrs 1 mth |
| Possession date extended | By 1 yr | 5 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Apr 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 67% | 97% |
| MahaRERA complaints (filed by or against the builder) | 19 | 6 |
The 5 projects
- Noble Heights, Malad East
- Shankeshwar Apartment, Malad East
- Sheetal Tapovan, Malad East
- Tower 28, Malad East
- Mauli Desire, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Noble Heights | August 2017 | April 2028 | 100% | 104 units booked out of total 114 units |
| Shankeshwar Apartment | August 2017 | April 2027 | 100% | 29 units booked out of total 106 units |
| Sheetal Tapovan | August 2017 | May 2024 | 100% | 264 units booked out of total 273 units |
| Tower 28 | August 2017 | June 2023 | 55% | 315 units booked out of total 321 units |
| Mauli Desire | July 2017 | June 2028 | 100% | 150 units booked out of total 152 units |
About this project
Green Acres by Nirman Realtors And Developers Ltd is a 180-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in August 2017 with possession due in December 2026. 120 units booked out of total 180 units. The concrete structure (RCC) is complete.
Read full summary
Green Acres is an SRA-sanctioned project by Nirman Realtors And Developers Ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800010794. It was launched in August 2017. It has 180 units in 1 building: 174 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.
120 units booked out of total 180 units (67%). Since the July 2026 update, 8 more units have been booked.