Astoria Tower B, Goregaon East
by Conwood Realty Private Limited · Goregaon East, Mumbai 400063 · Map
- Launched
- Sep 20173 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 7 yrs
- Concrete structure
- 35%Mid-construction
- Booked
- 141 of 14796%
- Buildings
- 10.9 acres
- MahaRERA complaints
- 8Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 20
- 2 BHK
- 21
- 3 BHK
- 84
- Other units
- 22
- Total units
- 147
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 9% | 141 | |
| 100% | 9% | 2% | 141 | |
| 100% | 9% | 2% | 141 | |
| 100% | 9% | 2% | 109 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400063
Projects with 60–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 6 yrs 4 mths |
| Possession date extended | By 7 yrs | 5 of 5 |
| Possession date (MahaRERA) | Dec 2027 | Jun 2026 |
| Concrete structure (RCC) | 35% | 93% |
| Units booked | 96% | 85% |
| MahaRERA complaints (filed by or against the builder) | 8 | 4 |
The 5 projects
- Samarth Tanish, Goregaon East
- Sky Villa, Goregaon East
- Delta House, Goregaon East
- Avant Hillway, Goregaon East
- Applaud-38, Goregaon East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Samarth Tanish | August 2017 | April 2027 | 100% | 133 units booked out of total 133 units |
| Sky Villa | August 2017 | December 2020 | 70% | 60 units booked out of total 89 units |
| Delta House | August 2017 | June 2026 | 100% | 151 units booked out of total 177 units |
| Avant Hillway | August 2017 | Apr 2027 | 33% | 132 units booked out of 146 units for sale |
| Applaud-38 | March 2018 | December 2025 | 93% | 137 units booked out of 205 units for sale |
About this project
Astoria Tower B by Conwood Realty Private Limited is a 147-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in September 2017 with possession due in December 2027. 141 units booked out of total 147 units. The concrete structure (RCC) is 35% complete.
Read full summary
Astoria Tower B is a BMC-sanctioned project by Conwood Realty Private Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800012007. It was launched in September 2017. It has 147 units in 1 building: 125 homes (1, 2 and 3 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 7 years from the original December 2020. Construction: excavation complete, structure (RCC) 35% complete, final finishes 9% complete.
141 units booked out of total 147 units (96%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 9% to 35% and the possession date has moved from December 2021 to December 2027.