Avant Hillway, Goregaon East
by Raghvendra Construction Company Pvt Ltd · Goregaon East, Mumbai 400063 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Apr 2027Extended in both phases
- Concrete structure
- 33%Weighted across 2 phases
- Booked (free sale)
- 132 of 14690%
- Buildings
- 41.2 acres
- MahaRERA complaints
- 15Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale132 booked out of 146 units
Land-owner share79 units, not for sale
Total 225 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 68
- 2 BHK
- 147
- 3 BHK
- 1
- Other units
- 9
- Total units
- 225
- Buildings
- 4
- Land
- 1.2 acres
- Phases
- 2
- MahaRERA complaints
- 15
- Free-sale units
- 146
- Land-owner share (not for sale)
- 79
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Avant Hillway Mid-construction | P51800010785 | 176 | 18% | 52% | |
| Avant Hillway Ready to move | P51800011215 | 40 | 100% | 88% |
Show updates by phase
Avant Hillway (P51800010785)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 67% | 18% | 0% | 97 | |
| 67% | 18% | 0% | – | |
| 67% | 18% | 0% | – | |
| 67% | 18% | 0% | 63 |
"–" means MahaRERA shows no figure for that update.
Avant Hillway (P51800011215)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 35 | |
| 100% | 100% | 100% | 35 | |
| 100% | 50% | 0% | – | |
| 100% | 50% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 5 similar projects in PIN 400063
Projects with 100–450 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 4 mths | 5 yrs 4 mths |
| Possession date extended | Yes | 4 of 5 |
| Possession date (MahaRERA) | Apr 2027 | Jun 2026 |
| Concrete structure (RCC) | 33% | 97% |
| Units booked (free sale) | 90% | 91% |
| MahaRERA complaints (filed by or against the builder) | 15 | 4 |
The 5 projects
- Delta House, Goregaon East
- Bhoomi Samarth, Goregaon East
- Samarth Tanish, Goregaon East
- Astoria Tower B, Goregaon East
- Applaud-38, Goregaon East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Delta House | August 2017 | June 2026 | 100% | 151 units booked out of total 177 units |
| Bhoomi Samarth | August 2017 | Dec 2021 – Jun 2025 | 97% | – |
| Samarth Tanish | August 2017 | April 2027 | 100% | 133 units booked out of total 133 units |
| Astoria Tower B | September 2017 | December 2027 | 35% | 141 units booked out of total 147 units |
| Applaud-38 | March 2018 | December 2025 | 93% | 137 units booked out of 205 units for sale |
About this project
Avant Hillway by Raghvendra Construction Company Pvt Ltd is a 225-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, registered with MahaRERA in 2 phases, with possession due in April 2027. 132 units booked out of 146 units for sale. The concrete structure (RCC) is 33% complete.
Read full summary
Avant Hillway is an SRA-sanctioned project by Raghvendra Construction Company Pvt Ltd in Goregaon East, Mumbai 400063, registered with MahaRERA as 2 phases (P51800010785, P51800011215). The first phase was launched in August 2017. Together the phases have 225 units in 4 buildings: 216 homes (1, 2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA. Of the 225 units, 146 are for sale and 79 are the land-owner's share, not for sale.
The registered possession date is April 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 33% complete and final finishes 19% complete. Neither phase has its structure complete.
132 units booked out of 146 units for sale (90%).