Samarth Tanish, Goregaon East
Ready to move
by Nitin Dattaram Samant · Goregaon East, Mumbai 400063 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 100%Ready to move
- Booked
- 133 of 133100%
- Buildings
- 10.4 acres
- MahaRERA complaints
- 14Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 133
- Total units
- 133
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 14
- Reserved units
- 69
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 133 | |
| 100% | 100% | 75% | 133 | |
| 100% | 100% | 75% | 133 | |
| 100% | 100% | 40% | 117 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400063
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 4 yrs 4 mths |
| Possession date extended | By 3 yrs 4 mths | 4 of 5 |
| Possession date (MahaRERA) | Apr 2027 | Jun 2026 |
| Concrete structure (RCC) | 100% | 70% |
| Units booked | 100% | 88% |
| MahaRERA complaints (filed by or against the builder) | 14 | 4 |
The 5 projects
- Delta House, Goregaon East
- Sky Villa, Goregaon East
- Avant Hillway, Goregaon East
- Bhoomi Samarth, Goregaon East
- Astoria Tower B, Goregaon East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Delta House | August 2017 | June 2026 | 100% | 151 units booked out of total 177 units |
| Sky Villa | August 2017 | December 2020 | 70% | 60 units booked out of total 89 units |
| Avant Hillway | August 2017 | Apr 2027 | 33% | 132 units booked out of 146 units for sale |
| Bhoomi Samarth | August 2017 | Dec 2021 – Jun 2025 | 97% | – |
| Astoria Tower B | September 2017 | December 2027 | 35% | 141 units booked out of total 147 units |
About this project
Samarth Tanish by Nitin Dattaram Samant is a 133-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in August 2017 with possession due in April 2027. 133 units booked out of total 133 units. The concrete structure (RCC) is complete.
Read full summary
Samarth Tanish is an SRA-sanctioned project by Nitin Dattaram Samant in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800003379. It was launched in August 2017. It has 133 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
133 units booked out of total 133 units (100%).