Luma, Andheri East

by Ecc-Konark Joint Venture · Andheri East, Mumbai 400059 · Map

Launched
Sep 2017First of 2 phases
Possession (MahaRERA)
Dec 2026 – Sep 2027Extended in 1 of 2 phases
Concrete structure
77%Weighted across 2 phases
Booked
225 of 30275% · 207 in Jul 2026
Buildings
30.3 acres
MahaRERA complaints
18Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
221
3 BHK
81
Total units
302
Buildings
3
Land
0.3 acres
Phases
2
MahaRERA complaints
18

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Luma Towers A & B
Ready to move
P51800012155129100%96%
Luma Tower C
Mid-construction
P5180005447217360%58%
Show updates by phase

Luma Towers A & B (P51800012155)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%124
100%100%70%120
33%31%0%–
33%13%0%102

"–" means MahaRERA shows no figure for that update.

Luma Tower C (P51800054472)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%101
80%0%0%87
80%0%0%67
20%0%0%47

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)77%
Finishes, lifts and services43%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 26%Dec 2025: Excavation 60%Jul 2026: Excavation 89%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 6%Dec 2025: Concrete structure (RCC) 13%Jul 2026: Concrete structure (RCC) 43%Oct 2026: Concrete structure (RCC) 77%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 30%Oct 2026: Final finishes 43%Excavation 100%Concrete structure (RCC) 77%Final finishes 43%

How to read construction stages

Compared with 4 similar projects in PIN 400059

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400059
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs4 yrs 6 mths
Possession date extendedYes3 of 4
Possession date (MahaRERA)Dec 2026 – Sep 2027Jun 2023
Concrete structure (RCC)77%81%
Units booked75%82%
MahaRERA complaints (filed by or against the builder)1811

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Luma by Ecc-Konark Joint Venture is a 302-unit SRA-sanctioned project in Andheri East, Mumbai 400059, registered with MahaRERA in 2 phases, with possession dates from December 2026 to September 2027. 225 units booked out of total 302 units. The concrete structure (RCC) is 77% complete.

Read full summary

Luma is an SRA-sanctioned project by Ecc-Konark Joint Venture in Andheri East, Mumbai 400059, registered with MahaRERA as 2 phases (P51800012155, P51800054472). The first phase was launched in September 2017. Together the phases have 302 units in 3 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from December 2026 to September 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 77% complete and final finishes 43% complete. Neither phase has its structure complete.

225 units booked out of total 302 units (75%). Since the July 2026 update, 18 more units have been booked.