Naman Premier, Andheri East

Lapsed

by Shree Naman Developers Pvt Ltd · Andheri East, Mumbai 400059 · Map

Launched
Aug 20172 yrs 7 mths originally promised
Possession (MahaRERA)
Mar 2021Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
357 of 43682%
Buildings
11.7 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
248
2 BHK
188
Total units
436
Buildings
1
Land
1.7 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services85%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 83%Dec 2025: Concrete structure (RCC) 83%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 83%Dec 2025: Final finishes 83%Jul 2026: Final finishes 85%Excavation 100%Concrete structure (RCC) 100%Final finishes 85%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%85%357
100%83%83%346
100%83%83%262

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400059

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400059
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths5 yrs 2 mths
Possession date extendedBy 1 yr3 of 4
Possession date (MahaRERA)Mar 2021Jun 2025
Concrete structure (RCC)100%78%
Units booked82%76%
MahaRERA complaints (filed by or against the builder)418

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Naman Premier by Shree Naman Developers Pvt Ltd is a 436-unit BMC-sanctioned project in Andheri East, Mumbai 400059, launched in August 2017; its MahaRERA registration has lapsed. 357 units booked out of total 436 units. The concrete structure (RCC) is complete.

Read full summary

Naman Premier is a BMC-sanctioned project by Shree Naman Developers Pvt Ltd in Andheri East, Mumbai 400059, registered with MahaRERA as P51800008002. It was launched in August 2017. It has 436 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2021, after an extension of 1 year from the original March 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.

357 units booked out of total 436 units (82%).