Skip to main content

Proxima Residences, Andheri East

Lapsed

by Aviation Hotels Pvt Ltd · Andheri East, Mumbai 400059 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 1 yrWhat does Lapsed mean?
Concrete structure
79%Mid-construction
Booked
253 of 33576%
Buildings
73.7 acres
MahaRERA complaints
24Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
171
3 BHK
121
4 BHK
1
Other units
41
Total units
335
Buildings
7
Land
3.7 acres
Phases
1
MahaRERA complaints
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)79%
Finishes, lifts and services26%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 79%Dec 2025: Concrete structure (RCC) 79%Jul 2026: Concrete structure (RCC) 79%Oct 2026: Concrete structure (RCC) 79%Dec 2024: Final finishes 26%Dec 2025: Final finishes 26%Jul 2026: Final finishes 26%Oct 2026: Final finishes 26%Excavation 100%Concrete structure (RCC) 79%Final finishes 26%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%26%253
100%79%26%–
100%79%26%–
100%79%26%253

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400059

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400059
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths4 yrs 4 mths
Possession date extendedBy 1 yr3 of 4
Possession date (MahaRERA)Dec 2023Dec 2024
Concrete structure (RCC)79%80%
Units booked76%82%
MahaRERA complaints (filed by or against the builder)2411

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Proxima Residences by Aviation Hotels Pvt Ltd is a 335-unit project in Andheri East, Mumbai 400059, launched in August 2017; its MahaRERA registration has lapsed. 253 units booked out of total 335 units. The concrete structure (RCC) is 79% complete.

Read full summary

Proxima Residences is a project by Aviation Hotels Pvt Ltd in Andheri East, Mumbai 400059, registered with MahaRERA as P51800005153. It was launched in August 2017. It has 335 units in 7 buildings: 294 homes (1, 2, 3 and 4 BHK) and 41 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 79% complete, final finishes 26% complete.

253 units booked out of total 335 units (76%).