Shri Upendra Chsl, Dahisar
by Harshal Enterprises · Dahisar, Mumbai 400068 · Map
- Launched
- Sep 20179 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 80%Mid-construction
- Booked
- 197 of 22886%
- Buildings
- 31.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 208
- 3 BHK
- 19
- Total units
- 228
- Buildings
- 3
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 33% | 197 | |
| 100% | 80% | 33% | – | |
| 100% | 80% | 33% | – | |
| 100% | 80% | 33% | 197 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400068
Projects with 100–500 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 9 yrs 3 mths | 4 yrs 8 mths |
| Possession date extended | No | 4 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Nov 2026 |
| Concrete structure (RCC) | 80% | 33% |
| Units booked | 86% | 52% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Earth Residency Wing C and Wing D, Dahisar
- Grandeur, Dahisar
- Sky Heights, Dahisar
- Guru Dwarka, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Earth Residency Wing C and Wing D | August 2017 | March 2029 | 0% | 0 units booked out of total 229 units |
| Grandeur | August 2017 | December 2025 | 88% | 103 units booked out of total 198 units |
| Sky Heights | August 2017 | Dec 2021 – Dec 2023 | 66% | – |
| Guru Dwarka | November 2017 | October 2027 | 0% | 161 units booked out of total 205 units |
About this project
Shri Upendra Chsl by Harshal Enterprises is a 228-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in September 2017 with possession due in December 2026. 197 units booked out of total 228 units. The concrete structure (RCC) is 80% complete.
Read full summary
Shri Upendra Chsl is a BMC-sanctioned project by Harshal Enterprises in Dahisar, Mumbai 400068, registered with MahaRERA as P51800013142. It was launched in September 2017. It has 228 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes 33% complete.
197 units booked out of total 228 units (86%).