Guru Dwarka, Dahisar
by Bsrd Infrabuild Private Limited · Dahisar, Mumbai 400068 · Map
- Launched
- Nov 20174 yrs 7 mths originally promised
- Possession (MahaRERA)
- Oct 2027Extended by 5 yrs 4 mths
- Concrete structure
- 0%Early stage
- Booked
- 161 of 20579%
- Buildings
- 30.7 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 136
- 2 BHK
- 68
- 3 BHK
- 1
- Total units
- 205
- Buildings
- 3
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Reserved units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 30% | 161 | |
| 100% | 0% | 30% | 161 | |
| 100% | 0% | 5% | 205 | |
| 100% | 0% | 5% | 156 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400068
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 7 mths | 5 yrs 4 mths |
| Possession date extended | By 5 yrs 4 mths | 3 of 4 |
| Possession date (MahaRERA) | Oct 2027 | Jun 2026 |
| Concrete structure (RCC) | 0% | 73% |
| Units booked | 79% | 52% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Shri Upendra Chsl, Dahisar
- Grandeur, Dahisar
- Earth Residency Wing C and Wing D, Dahisar
- Sky Heights, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shri Upendra Chsl | September 2017 | December 2026 | 80% | 197 units booked out of total 228 units |
| Grandeur | August 2017 | December 2025 | 88% | 103 units booked out of total 198 units |
| Earth Residency Wing C and Wing D | August 2017 | March 2029 | 0% | 0 units booked out of total 229 units |
| Sky Heights | August 2017 | Dec 2021 – Dec 2023 | 66% | – |
About this project
Guru Dwarka by Bsrd Infrabuild Private Limited is a 205-unit SRA-sanctioned project in Dahisar, Mumbai 400068, launched in November 2017 with possession due in October 2027. 161 units booked out of total 205 units. Work on the concrete structure (RCC) has not started.
Read full summary
Guru Dwarka is an SRA-sanctioned project by Bsrd Infrabuild Private Limited in Dahisar, Mumbai 400068, registered with MahaRERA as P51800014414. It was launched in November 2017. It has 205 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2027, extended by 5 years 4 months from the original June 2022. Construction: excavation complete, structure (RCC) not started, final finishes 30% complete.
161 units booked out of total 205 units (79%).