- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 4 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 88%Mid-construction
- Booked
- 103 of 19852%
- Buildings
- 11.7 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 2
- 1 BHK
- 75
- 2 BHK
- 2
- 3 BHK
- 63
- 4 BHK
- 56
- Total units
- 198
- Buildings
- 1
- Land
- 1.7 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 88% | 63% | 103 | |
| 100% | 88% | 63% | – | |
| 100% | 88% | 63% | – | |
| 100% | 77% | 43% | 103 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400068
Projects with 90–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 5 yrs 4 mths |
| Possession date extended | By 4 yrs 6 mths | 3 of 4 |
| Possession date (MahaRERA) | Dec 2025 | May 2027 |
| Concrete structure (RCC) | 88% | 33% |
| Units booked | 52% | 79% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Earth Residency Wing C and Wing D, Dahisar
- Sky Heights, Dahisar
- Shri Upendra Chsl, Dahisar
- Guru Dwarka, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Earth Residency Wing C and Wing D | August 2017 | March 2029 | 0% | 0 units booked out of total 229 units |
| Sky Heights | August 2017 | Dec 2021 – Dec 2023 | 66% | – |
| Shri Upendra Chsl | September 2017 | December 2026 | 80% | 197 units booked out of total 228 units |
| Guru Dwarka | November 2017 | October 2027 | 0% | 161 units booked out of total 205 units |
About this project
Grandeur by Sunrise Associates is a 198-unit project in Dahisar, Mumbai 400068, launched in August 2017; its MahaRERA registration has lapsed. 103 units booked out of total 198 units. The concrete structure (RCC) is 88% complete.
Read full summary
Grandeur is a project by Sunrise Associates in Dahisar, Mumbai 400068, registered with MahaRERA as P51800011102. It was launched in August 2017. It has 198 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025, after an extension of 4 years 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 88% complete, final finishes 63% complete.
103 units booked out of total 198 units (52%).