73 East, Kandivali West

Ready to move

by Dimple Realtors Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Feb 20187 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Ready to move
Booked
150 of 21869%
Buildings
11.1 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
132
3 BHK
70
4 BHK
8
5+ BHK
5
Other units
3
Total units
218
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 95%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 11%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%150
100%100%90%132
100%95%11%99

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400067

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 10 mths5 yrs 4 mths
Possession date extendedBy 1 yr4 of 4
Possession date (MahaRERA)Dec 2026May 2026
Concrete structure (RCC)100%96%
Units booked69%73%
MahaRERA complaints (filed by or against the builder)23

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

73 East by Dimple Realtors Private Limited is a 218-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in February 2018 with possession due in December 2026. 150 units booked out of total 218 units. The concrete structure (RCC) is complete.

Read full summary

73 East is an SRA-sanctioned project by Dimple Realtors Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800015343. It was launched in February 2018. It has 218 units in 1 building: 215 homes (2, 3, 4 and 5+ BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

150 units booked out of total 218 units (69%).