Shiv Parvati Chs Ltd Phase -1, Kandivali West

by Jayeshjagruti Developers Pvt Ltd · Kandivali West, Mumbai 400067 · Map

Launched
Oct 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 7 yrs 1 mth
Concrete structure
100%Nearing possession
Booked (free sale)
144 of 20570%
Buildings
41.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale144 booked out of 205 units

Land-owner share107 units, not for sale

Total 312 units. Land-owner units are not for sale.

Project facts

2 BHK
274
3 BHK
38
Total units
312
Buildings
4
Land
1.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
205
Land-owner share (not for sale)
107

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services78%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 99%Dec 2025: Excavation 98%Jul 2026: Excavation 98%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 95%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 52%Dec 2025: Final finishes 65%Jul 2026: Final finishes 65%Oct 2026: Final finishes 78%Excavation 100%Concrete structure (RCC) 100%Final finishes 78%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%78%144
98%95%65%–
98%95%65%–
99%95%52%120

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 150–700 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths4 yrs 10 mths
Possession date extendedBy 7 yrs 1 mth6 of 6
Possession date (MahaRERA)Apr 2027Dec 2025
Concrete structure (RCC)100%96%
Units booked (free sale)70%77%
MahaRERA complaints (filed by or against the builder)016

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shiv Parvati Chs Ltd Phase -1 by Jayeshjagruti Developers Pvt Ltd is a 312-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in October 2017 with possession due in April 2027. 144 units booked out of 205 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shiv Parvati Chs Ltd Phase -1 is a MHADA-sanctioned project by Jayeshjagruti Developers Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800013524. It was launched in October 2017. It has 312 units in 4 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 312 units, 205 are for sale and 107 are the land-owner's share, not for sale.

Its registered possession date is April 2027, extended by 7 years 1 month from the original March 2020. Construction: excavation complete, structure (RCC) complete, final finishes 78% complete.

144 units booked out of 205 units for sale (70%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 95% to 100% and the possession date has moved from March 2020 to April 2027.