Shiv Parvati Chs Ltd Phase -1, Kandivali West
by Jayeshjagruti Developers Pvt Ltd · Kandivali West, Mumbai 400067 · Map
- Launched
- Oct 20172 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 7 yrs 1 mth
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 144 of 20570%
- Buildings
- 41.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale144 booked out of 205 units
Land-owner share107 units, not for sale
Total 312 units. Land-owner units are not for sale.
Project facts
- 2 BHK
- 274
- 3 BHK
- 38
- Total units
- 312
- Buildings
- 4
- Land
- 1.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 205
- Land-owner share (not for sale)
- 107
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 78% | 144 | |
| 98% | 95% | 65% | – | |
| 98% | 95% | 65% | – | |
| 99% | 95% | 52% | 120 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 150–700 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 4 yrs 10 mths |
| Possession date extended | By 7 yrs 1 mth | 6 of 6 |
| Possession date (MahaRERA) | Apr 2027 | Dec 2025 |
| Concrete structure (RCC) | 100% | 96% |
| Units booked (free sale) | 70% | 77% |
| MahaRERA complaints (filed by or against the builder) | 0 | 16 |
The 6 projects
- Dharti Pressidio, Kandivali West
- Ruparel Skygreens I, Kandivali West
- Meridian Court 1, Kandivali West
- Avenue, Kandivali West
- 73 East, Kandivali West
- Shivraj Heights, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dharti Pressidio | September 2017 | December 2022 | 100% | 235 units booked out of total 235 units |
| Ruparel Skygreens I | September 2017 | December 2026 | 100% | 405 units booked out of total 481 units |
| Meridian Court 1 | August 2017 | April 2028 | 8% | 221 units booked out of total 373 units |
| Avenue | July 2017 | Dec 2024 – Dec 2029 | 67% | – |
| 73 East | February 2018 | December 2026 | 100% | 150 units booked out of total 218 units |
| Shivraj Heights | May 2018 | Dec 2023 – Mar 2027 | 91% | 160 units booked out of total 209 units |
About this project
Shiv Parvati Chs Ltd Phase -1 by Jayeshjagruti Developers Pvt Ltd is a 312-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in October 2017 with possession due in April 2027. 144 units booked out of 205 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shiv Parvati Chs Ltd Phase -1 is a MHADA-sanctioned project by Jayeshjagruti Developers Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800013524. It was launched in October 2017. It has 312 units in 4 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 312 units, 205 are for sale and 107 are the land-owner's share, not for sale.
Its registered possession date is April 2027, extended by 7 years 1 month from the original March 2020. Construction: excavation complete, structure (RCC) complete, final finishes 78% complete.
144 units booked out of 205 units for sale (70%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 95% to 100% and the possession date has moved from March 2020 to April 2027.