Shivraj Heights, Kandivali West
by Kailash Punwasi Yadav · Kandivali West, Mumbai 400067 · Map
- Launched
- May 2018First of 2 phases
- Possession (MahaRERA)
- Dec 2023 – Mar 2027Extended in 1 of 2 phases
- Concrete structure
- 91%Weighted across 2 phases
- Booked
- 160 of 20977%
- Buildings
- 30.9 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 136
- 2 BHK
- 67
- Other units
- 6
- Total units
- 209
- Buildings
- 3
- Land
- 0.9 acres
- Phases
- 2
- MahaRERA complaints
- 6
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Shivraj Heights Mid-construction Lapsed | P51800016497 | 136 | 87% | 87% | |
| Shivraj Heights Wing C Nearing possession | P51800046085 | 67 | 100% | 54% |
Show updates by phase
Shivraj Heights (P51800016497)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 0% | 124 | |
| 100% | 87% | 0% | – | |
| 100% | 87% | 0% | – | |
| 100% | 87% | 0% | 124 |
"–" means MahaRERA shows no figure for that update.
Shivraj Heights Wing C (P51800046085)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 36 | |
| 100% | 100% | 50% | 36 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400067
Projects with 100–450 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 6 mths | 6 yrs 2 mths |
| Possession date extended | Yes | 3 of 3 |
| Possession date (MahaRERA) | Dec 2023 – Mar 2027 | Apr 2027 |
| Concrete structure (RCC) | 91% | 100% |
| Units booked | 77% | 69% |
| MahaRERA complaints (filed by or against the builder) | 6 | 0 |
The 3 projects
- 73 East, Kandivali West
- New Sailee Heritage, Kandivali West
- Shiv Parvati Chs Ltd Phase -1, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| 73 East | February 2018 | December 2026 | 100% | 150 units booked out of total 218 units |
| New Sailee Heritage | August 2018 | October 2029 | 15% | 17 units booked out of 81 units for sale |
| Shiv Parvati Chs Ltd Phase -1 | October 2017 | April 2027 | 100% | 144 units booked out of 205 units for sale |
About this project
Shivraj Heights by Kailash Punwasi Yadav is a 209-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, registered with MahaRERA in 2 phases, with possession dates from December 2023 to March 2027. 160 units booked out of total 209 units. The concrete structure (RCC) is 91% complete.
Read full summary
Shivraj Heights is an SRA-sanctioned project by Kailash Punwasi Yadav in Kandivali West, Mumbai 400067, registered with MahaRERA as 2 phases (P51800016497, P51800046085). The first phase was launched in May 2018. Together the phases have 209 units in 3 buildings: 203 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.
The phases' registered possession dates run from December 2023 to March 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 91% complete and final finishes 17% complete. Neither phase has its structure complete.
160 units booked out of total 209 units (77%).