by Kailash Punwasi Yadav · Kandivali West, Mumbai 400067 · Map

Launched
May 2018First of 2 phases
Possession (MahaRERA)
Dec 2023 – Mar 2027Extended in 1 of 2 phases
Concrete structure
91%Weighted across 2 phases
Booked
160 of 20977%
Buildings
30.9 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
136
2 BHK
67
Other units
6
Total units
209
Buildings
3
Land
0.9 acres
Phases
2
MahaRERA complaints
6

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Shivraj Heights
Mid-construction Lapsed
P5180001649713687%87%
Shivraj Heights Wing C
Nearing possession
P5180004608567100%54%
Show updates by phase

Shivraj Heights (P51800016497)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%87%0%124
100%87%0%–
100%87%0%–
100%87%0%124

"–" means MahaRERA shows no figure for that update.

Shivraj Heights Wing C (P51800046085)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%36
100%100%50%36
100%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)91%
Finishes, lifts and services17%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 58%Dec 2025: Concrete structure (RCC) 58%Jul 2026: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 91%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 17%Oct 2026: Final finishes 17%Excavation 100%Concrete structure (RCC) 91%Final finishes 17%

How to read construction stages

Compared with 3 similar projects in PIN 400067

Projects with 100–450 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths6 yrs 2 mths
Possession date extendedYes3 of 3
Possession date (MahaRERA)Dec 2023 – Mar 2027Apr 2027
Concrete structure (RCC)91%100%
Units booked77%69%
MahaRERA complaints (filed by or against the builder)60

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Shivraj Heights by Kailash Punwasi Yadav is a 209-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, registered with MahaRERA in 2 phases, with possession dates from December 2023 to March 2027. 160 units booked out of total 209 units. The concrete structure (RCC) is 91% complete.

Read full summary

Shivraj Heights is an SRA-sanctioned project by Kailash Punwasi Yadav in Kandivali West, Mumbai 400067, registered with MahaRERA as 2 phases (P51800016497, P51800046085). The first phase was launched in May 2018. Together the phases have 209 units in 3 buildings: 203 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from December 2023 to March 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 91% complete and final finishes 17% complete. Neither phase has its structure complete.

160 units booked out of total 209 units (77%).