Aureate, Bhandup West

by Beauty Ganraj Construction LLP · Bhandup West, Mumbai 400078 · Map

Launched
Dec 20196 yrs originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Nearing possession
Booked (free sale)
51 of 5396% · 55 rehab units
Buildings
10.8 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale51 booked out of 53 units

Rehab55 units for existing members

Total 108 units. Rehab units are not for sale.

Project facts

1 RK
13
1 BHK
69
2 BHK
24
Other units
2
Total units
108
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
1
Free-sale units
53
Rehab units
55

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 40%Dec 2025: Excavation 40%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 25%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%51
100%100%25%51
40%0%0%–
40%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400078

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs5 yrs 11 mths
Possession date extendedBy 1 yr1 of 3
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Aureate by Beauty Ganraj Construction LLP is a 108-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in December 2019 with possession due in December 2026. 51 units booked out of 53 units for sale. The concrete structure (RCC) is complete.

Read full summary

Aureate is an SRA-sanctioned project by Beauty Ganraj Construction LLP in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800023266. It was launched in December 2019. It has 108 units in 1 building: 106 homes (1 RK, 1 BHK and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 108 units, 53 are for sale and 55 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.

51 units booked out of 53 units for sale (96%).