Aniraj Tower Chs Ltd, Bhandup West

by Sudhanshu Infrastructures Private Limited · Bhandup West, Mumbai 400078 · Map

Launched
Feb 20205 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 2 yrs
Concrete structure
25%Mid-construction
Booked (free sale)
81 of 20839% · 66 rehab units
Buildings
10.8 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale81 booked out of 208 units

Rehab66 units for existing members

Total 274 units. Rehab units are not for sale.

Project facts

1 BHK
104
2 BHK
68
3 BHK
18
Other units
84
Total units
274
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
3
Free-sale units
208
Rehab units
66

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)25%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 25%Dec 2024: Final finishes 0%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Excavation 100%Final finishes 30%Concrete structure (RCC) 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%30%81
100%25%30%81
100%20%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400078

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 10 mths6 yrs
Possession date extendedBy 2 yrs2 of 4
Possession date (MahaRERA)Dec 2027Dec 2026
Concrete structure (RCC)25%100%
Units booked (free sale)39%95%
MahaRERA complaints (filed by or against the builder)30

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Aniraj Tower Chs Ltd by Sudhanshu Infrastructures Private Limited is a 274-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in February 2020 with possession due in December 2027. 81 units booked out of 208 units for sale. The concrete structure (RCC) is 25% complete.

Read full summary

Aniraj Tower Chs Ltd is an SRA-sanctioned project by Sudhanshu Infrastructures Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800024276. It was launched in February 2020. It has 274 units in 1 building: 190 homes (1, 2 and 3 BHK) and 84 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 274 units, 208 are for sale and 66 are rehab units for existing members.

Its registered possession date is December 2027, extended by 2 years from the original December 2025. Construction: excavation complete, structure (RCC) 25% complete, final finishes 30% complete.

81 units booked out of 208 units for sale (39%).