Fairmont, Bhandup West

by Trident Ozone LLP · Bhandup West, Mumbai 400078 · Map

Launched
Mar 20206 yrs 9 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
113 of 12193% · 90 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale113 booked out of 121 units

Rehab90 units for existing members

Total 211 units. Rehab units are not for sale.

Project facts

1 BHK
196
Other units
15
Total units
211
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
121
Rehab units
90

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 40%Jul 2026: Final finishes 65%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%113
100%100%65%109
100%100%40%105
100%100%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400078

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 9 mths5 yrs 11 mths
Possession date extendedNo3 of 4
Possession date (MahaRERA)Dec 2026Mar 2027
Concrete structure (RCC)100%100%
Units booked (free sale)93%95%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Fairmont by Trident Ozone LLP is a 211-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in March 2020 with possession due in December 2026. 113 units booked out of 121 units for sale. The concrete structure (RCC) is complete.

Read full summary

Fairmont is an SRA-sanctioned project by Trident Ozone LLP in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800024818. It was launched in March 2020. It has 211 units in 2 buildings: 196 homes (1 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 211 units, 121 are for sale and 90 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

113 units booked out of 121 units for sale (93%). Since the July 2026 update, 4 more units have been booked.