Ruparel Livia, Kurla East
Lapsed
by Shree Siddhivinayak Classic Construction Private Limited · Kurla East, Mumbai 400024 · Map
- Launched
- Sep 20203 yrs 9 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 151 of 15597%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 9Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 120
- Other units
- 35
- Total units
- 155
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 9
- Reserved units
- 85
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 151 | |
| 100% | 100% | 0% | 151 | |
| 100% | 43% | 0% | – | |
| 100% | 43% | 0% | 61 |
"–" means MahaRERA shows no figure for that update.
About this project
Ruparel Livia by Shree Siddhivinayak Classic Construction Private Limited (Ruparel) is a 155-unit SRA-sanctioned project in Kurla East, Mumbai 400024, launched in September 2020; its MahaRERA registration has lapsed. 151 units booked out of total 155 units. The concrete structure (RCC) is complete.
Read full summary
Ruparel Livia is an SRA-sanctioned project by Shree Siddhivinayak Classic Construction Private Limited in Kurla East, Mumbai 400024, registered with MahaRERA as P51800026450. It was launched in September 2020. It has 155 units in 1 building: 120 homes (1 BHK) and 35 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 2 years from the original June 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.
151 units booked out of total 155 units (97%).
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.