Solaris 14th Floor, Andheri East

Lapsed

by Hubtown Limited · Andheri East, Mumbai 400093 · Map

Launched
Feb 20215 yrs 4 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
11.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
19
Total units
19
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services56%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 56%Dec 2025: Final finishes 56%Jul 2026: Final finishes 56%Oct 2026: Final finishes 56%Excavation 100%Final finishes 56%Concrete structure (RCC) 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%56%–
100%0%56%–
100%0%56%–
100%0%56%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Solaris 14th Floor by Hubtown Limited is a 19-unit project in Andheri East, Mumbai 400093, launched in February 2021; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Solaris 14th Floor is a project by Hubtown Limited in Andheri East, Mumbai 400093, registered with MahaRERA as P51800028276. It was launched in February 2021. It has 19 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes 56% complete.

Hubtown's track record in Mumbai

MahaRERA projects registered 2017–2023 in Mumbai

Projects registered with MahaRERA27
Total units across these projects1,419
Completed without extending the possession date11
Completed after an extension0
Lapsed10
Under construction6
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Hubtown projects234 (14 of 27 projects)

See all Hubtown projects →