Mahindra Alcove, Chandivali

Lapsed

by Mahindra Lifespace Developers limited · Chandivali, Mumbai 400072 · Map

Launched
Feb 2021First of 3 phases
Possession (MahaRERA)
Dec 2025 – Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
36%Weighted across 3 phases
Booked
–
Buildings
52.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
91
2 BHK
203
3 BHK
45
Total units
339
Buildings
5
Land
2.3 acres
Phases
3
MahaRERA complaints
1

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Mahindra Alcove Wing D And E
Early stage Lapsed
P518000283521550%–
Mahindra Alcove Wing B
Early stage Lapsed
P51800031699620%77%
Mahindra Alcove Wing A And C
Nearing possession Lapsed
P51800033573122100%87%
Show updates by phase

Mahindra Alcove Wing D And E (P51800028352)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%106

"–" means MahaRERA shows no figure for that update.

Mahindra Alcove Wing B (P51800031699)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%48
100%0%0%48
100%0%0%–
100%0%0%29

"–" means MahaRERA shows no figure for that update.

Mahindra Alcove Wing A And C (P51800033573)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%89%106
100%0%0%–
100%0%0%–
100%0%0%82

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)36%
Finishes, lifts and services32%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 36%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 32%Excavation 100%Concrete structure (RCC) 36%Final finishes 32%

How to read construction stages

About this project

Mahindra Alcove by Mahindra Lifespace Developers limited (Mahindra Lifespaces) is a 339-unit BMC-sanctioned project in Chandivali, Mumbai 400072, registered with MahaRERA in 3 phases, with possession dates from December 2025 to June 2026. The concrete structure (RCC) is 36% complete.

Read full summary

Mahindra Alcove is a BMC-sanctioned project by Mahindra Lifespace Developers limited in Chandivali, Mumbai 400072, registered with MahaRERA as 3 phases (P51800028352, P51800031699, P51800033573). The first phase was launched in February 2021. Together the phases have 339 units in 5 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. All 3 phases are lapsed on MahaRERA.

The phases' registered possession dates run from December 2025 to June 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 36% complete and final finishes 32% complete. 1 of the 3 phases has its structure complete.

Mahindra Lifespaces's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA17
Total units across these projects4,150
Completed without extending the possession date4
Completed after an extension2
Lapsed3
Under construction8
Possession date extended on the builder's application2
Typical time from launch to 100% structure5 years 4 months
MahaRERA complaints (filed by or against the builder), all Mahindra Lifespaces projects4 (4 of 17 projects)

See all Mahindra Lifespaces projects →