Kshitij Eminence, Bhandup West

Ready to moveLapsed

by Kshitij Developers · Bhandup West, Mumbai 400078 · Map

Launched
Mar 20215 yrs 3 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
38 of 5470%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale38 booked out of 54 units

Land-owner share51 units, not for sale

Total 105 units. Land-owner units are not for sale.

Project facts

1 BHK
32
2 BHK
32
3 BHK
6
Other units
35
Total units
105
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
54
Land-owner share (not for sale)
51

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%38
0%0%0%35
0%0%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400078

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 3 mths2 yrs 11 mths
Possession date extendedNo3 of 3
Possession date (MahaRERA)Jun 2026Apr 2027
Concrete structure (RCC)100%90%
Units booked (free sale)70%57%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Kshitij Eminence by Kshitij Developers is a 105-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in March 2021; its MahaRERA registration has lapsed. 38 units booked out of 54 units for sale. The concrete structure (RCC) is complete.

Read full summary

Kshitij Eminence is a BMC-sanctioned project by Kshitij Developers in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800028688. It was launched in March 2021. It has 105 units in 1 building: 70 homes (1, 2 and 3 BHK) and 35 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 105 units, 54 are for sale and 51 are the land-owner's share, not for sale.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

38 units booked out of 54 units for sale (70%).