Pranay Apsara, Dahisar

Lapsed

by Pranay Real Estate Developers · Dahisar, Mumbai 400068 · Map

Launched
Apr 20213 yrs 8 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 1 yrWhat does Lapsed mean?
Concrete structure
61%Mid-construction
Booked
33 of 12127%
Buildings
20.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
98
Other units
23
Total units
121
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)61%
Finishes, lifts and services5%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 45%Jul 2026: Concrete structure (RCC) 61%Oct 2026: Concrete structure (RCC) 61%Dec 2024: Final finishes 3%Dec 2025: Final finishes 5%Jul 2026: Final finishes 5%Oct 2026: Final finishes 5%Excavation 100%Concrete structure (RCC) 61%Final finishes 5%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%61%5%33
100%61%5%33
100%45%5%34
100%20%3%96

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400068

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 10 mths
Possession date extendedBy 1 yr3 of 4
Possession date (MahaRERA)Dec 2025Aug 2026
Concrete structure (RCC)61%38%
Units booked27%70%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Pranay Apsara by Pranay Real Estate Developers is a 121-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in April 2021; its MahaRERA registration has lapsed. 33 units booked out of total 121 units. The concrete structure (RCC) is 61% complete.

Read full summary

Pranay Apsara is a BMC-sanctioned project by Pranay Real Estate Developers in Dahisar, Mumbai 400068, registered with MahaRERA as P51800029019. It was launched in April 2021. It has 121 units in 2 buildings: 98 homes (1 BHK) and 23 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 1 year from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 61% complete, final finishes 5% complete.

33 units booked out of total 121 units (27%).