Royal Stone, Vikhroli

by VaibhavLaxmi Builders and Developers · Vikhroli, Mumbai 400083 · Map

Launched
Jul 20212 yrs 5 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 4 yrs
Concrete structure
67%Mid-construction
Booked (free sale)
147 of 15893% · 32 rehab units
Buildings
30.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale147 booked out of 158 units

Rehab32 units for existing members

Total 190 units. Rehab units are not for sale.

Project facts

1 BHK
66
2 BHK
105
Other units
19
Total units
190
Buildings
3
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
158
Rehab units
32
Reserved units
28

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation80%
Concrete structure (slabs)67%
Finishes, lifts and services67%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 67%Dec 2025: Excavation 80%Jul 2026: Excavation 80%Oct 2026: Excavation 80%Dec 2024: Concrete structure (RCC) 67%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 67%Oct 2026: Concrete structure (RCC) 67%Dec 2024: Final finishes 67%Dec 2025: Final finishes 67%Jul 2026: Final finishes 67%Oct 2026: Final finishes 67%Excavation 80%Concrete structure (RCC) 67%Final finishes 67%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%67%67%147
80%67%67%–
80%67%67%–
67%67%67%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400083

Projects with 80–350 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths4 yrs 3 mths
Possession date extendedBy 4 yrs1 of 5
Possession date (MahaRERA)Dec 2027Dec 2025
Concrete structure (RCC)67%100%
Units booked (free sale)93%87%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Royal Stone by VaibhavLaxmi Builders and Developers is a 190-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in July 2021 with possession due in December 2027. 147 units booked out of 158 units for sale. The concrete structure (RCC) is 67% complete.

Read full summary

Royal Stone is a MHADA-sanctioned project by VaibhavLaxmi Builders and Developers in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800029854. It was launched in July 2021. It has 190 units in 3 buildings: 171 homes (1 and 2 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 190 units, 158 are for sale and 32 are rehab units for existing members.

Its registered possession date is December 2027, extended by 4 years from the original December 2023. Construction: excavation 80% complete, structure (RCC) 67% complete, final finishes 67% complete.

147 units booked out of 158 units for sale (93%). Since the July 2026 update, the possession date has moved from November 2024 to December 2027.