- Launched
- Aug 20214 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 86
- 2 BHK
- 64
- Total units
- 150
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400083
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 4 yrs |
| Possession date extended | No | 2 of 5 |
| Possession date (MahaRERA) | Dec 2025 | Dec 2025 |
| Concrete structure (RCC) | 0% | 100% |
| Units booked | – | 93% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Royal Stone, Vikhroli
- Bliss, Vikhroli
- Shree Balaji 7, Vikhroli
- Adityaraj Royale, Vikhroli
- Peak 25, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Royal Stone | July 2021 | December 2027 | 67% | 147 units booked out of 158 units for sale |
| Bliss | October 2021 | December 2025 | 100% | 115 units booked out of total 121 units |
| Shree Balaji 7 | December 2021 | January 2028 | 95% | 98 units booked out of 118 units for sale |
| Adityaraj Royale | December 2021 | December 2025 | 100% | 135 units booked out of total 160 units |
| Peak 25 | January 2022 | December 2025 | 100% | 85 units booked out of 88 units for sale |
About this project
Adityaraj Signature by Adityaraj Enterprises Nx is a 150-unit project in Vikhroli, Mumbai 400083, launched in August 2021; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.
Read full summary
Adityaraj Signature is a project by Adityaraj Enterprises Nx in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800030225. It was launched in August 2021. It has 150 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.
Adityaraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 29 |
|---|---|
| Total units across these projects | 3,149 |
| Completed without extending the possession date | 7 |
| Completed after an extension | 2 |
| Lapsed | 10 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 3 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Adityaraj projects | 2 (2 of 29 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.