Bliss, Vikhroli

Lapsed

by Kripa Elite Corporation · Vikhroli, Mumbai 400083 · Map

Launched
Oct 20214 yrs 2 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
115 of 12195%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
65
2 BHK
56
Total units
121
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%115
100%100%50%–
100%100%50%–
100%100%50%115

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400083

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths4 yrs
Possession date extendedNo2 of 5
Possession date (MahaRERA)Dec 2025Dec 2025
Concrete structure (RCC)100%95%
Units booked95%89%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Bliss by Kripa Elite Corporation is a 121-unit project in Vikhroli, Mumbai 400083, launched in October 2021; its MahaRERA registration has lapsed. 115 units booked out of total 121 units. The concrete structure (RCC) is complete.

Read full summary

Bliss is a project by Kripa Elite Corporation in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800031607. It was launched in October 2021. It has 121 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

115 units booked out of total 121 units (95%).