Padma Apartment Co-Operative Housing Society Limited, Dahisar

by Haritara Construction Company Private Limited · Dahisar, Mumbai 400068 · Map

Launched
Oct 20212 yrs 11 mths originally promised
Possession (MahaRERA)
Sep 2026Extended by 2 yrs
Concrete structure
90%Mid-construction
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
7
2 BHK
5
Other units
3
Total units
15
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%–
100%90%0%–
100%90%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400068

Projects with up to 30 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths1 yr 9 mths
Possession date extendedBy 2 yrs2 of 5
Possession date (MahaRERA)Sep 2026Dec 2024
Concrete structure (RCC)90%70%
Units booked–34%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Padma Apartment Co-Operative Housing Society Limited by Haritara Construction Company Private Limited is a 15-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in October 2021 with possession due in September 2026. The concrete structure (RCC) is 90% complete.

Read full summary

Padma Apartment Co-Operative Housing Society Limited is a BMC-sanctioned project by Haritara Construction Company Private Limited in Dahisar, Mumbai 400068, registered with MahaRERA as P51800031219. It was launched in October 2021. It has 15 units in 1 building: 12 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in September 2026, after an extension of 2 years from the original September 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.