Shiv Shreyas Chsl, Dahisar

Lapsed

by K P Developers · Dahisar, Mumbai 400068 · Map

Launched
Mar 20223 yrs 9 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
70%Mid-construction
Booked (free sale)
1 of 119% · 7 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 11 units

Rehab7 units for existing members

Total 18 units. Rehab units are not for sale.

Project facts

1 BHK
3
2 BHK
12
3 BHK
3
Total units
18
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Rehab units
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%1
0%0%0%1
0%0%0%1
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with up to 40 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths2 yrs 2 mths
Possession date extendedNo4 of 6
Possession date (MahaRERA)Dec 2025Nov 2025
Concrete structure (RCC)70%65%
Units booked (free sale)9%34%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shiv Shreyas Chsl by K P Developers is an 18-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in March 2022; its MahaRERA registration has lapsed. 1 unit booked out of 11 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

Shiv Shreyas Chsl is a BMC-sanctioned project by K P Developers in Dahisar, Mumbai 400068, registered with MahaRERA as P51800033758. It was launched in March 2022. It has 18 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 18 units, 11 are for sale and 7 are rehab units for existing members.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.

1 unit booked out of 11 units for sale (9%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 70%.