Datta Leela Residency, Dahisar

Lapsed

by Swarupa Construction · Dahisar, Mumbai 400068 · Map

Launched
Jun 20216 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 3 yrsWhat does Lapsed mean?
Concrete structure
90%Mid-construction
Booked
6 of 1443%
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
13
Total units
14
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%6
100%90%0%–
100%90%0%–
100%90%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400068

Projects with up to 30 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 mths2 yrs 11 mths
Possession date extendedBy 3 yrs2 of 3
Possession date (MahaRERA)Dec 2024Sep 2026
Concrete structure (RCC)90%70%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Datta Leela Residency by Swarupa Construction is a 14-unit project in Dahisar, Mumbai 400068, launched in June 2021; its MahaRERA registration has lapsed. 6 units booked out of total 14 units. The concrete structure (RCC) is 90% complete.

Read full summary

Datta Leela Residency is a project by Swarupa Construction in Dahisar, Mumbai 400068, registered with MahaRERA as P51800029654. It was launched in June 2021. It has 14 units in 1 building, with 1 RK and 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 3 years from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.

6 units booked out of total 14 units (43%).