Skip to main content

72 Marina - Phase I - Tierra and Torres, Chandivali

by D S Developers · Chandivali, Mumbai 400072 · Map

Launched
Feb 20224 yrs 10 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
136 of 14693% · 20 rehab units
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale136 booked out of 146 units

Rehab20 units for existing members

Total 166 units. Rehab units are not for sale.

Project facts

1 BHK
73
2 BHK
93
Total units
166
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
146
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 38%Jul 2026: Concrete structure (RCC) 77%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%136
100%77%0%136
100%38%0%134
100%0%0%113

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400072

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400072
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths3 yrs 6 mths
Possession date extendedNo2 of 4
Possession date (MahaRERA)Dec 2026Jun 2026
Concrete structure (RCC)100%100%
Units booked (free sale)93%85%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

72 Marina - Phase I - Tierra and Torres by D S Developers is a 166-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in February 2022 with possession due in December 2026. 136 units booked out of 146 units for sale. The concrete structure (RCC) is complete.

Read full summary

72 Marina - Phase I - Tierra and Torres is a BMC-sanctioned project by D S Developers in Chandivali, Mumbai 400072, registered with MahaRERA as P51800032960. It was launched in February 2022. It has 166 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 166 units, 146 are for sale and 20 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

136 units booked out of 146 units for sale (93%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 77% to 100%.