Pride Panorama, Chandivali

by Landcare Realty LLP · Chandivali, Mumbai 400072 · Map

Launched
Apr 2022First of 2 phases
Possession (MahaRERA)
Dec 2025 – Dec 2026Not extended
Concrete structure
100%Weighted across 2 phases
Booked
34 of 27412%
Buildings
60.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
97
2 BHK
102
3 BHK
59
Other units
15
Total units
274
Buildings
6
Land
0.6 acres
Phases
2
MahaRERA complaints
1

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Pride Panorama
Ready to move Lapsed
P51800034548141100%16%
Pride Panorama
Nearing possession
P51800048083118100%8%
Show updates by phase

Pride Panorama (P51800034548)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%24
100%100%89%–
100%75%56%–
98%0%0%24

"–" means MahaRERA shows no figure for that update.

Pride Panorama (P51800048083)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%10
100%100%0%–
100%0%0%–
100%0%0%10

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services54%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 99%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 41%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 30%Jul 2026: Final finishes 48%Oct 2026: Final finishes 54%Excavation 100%Concrete structure (RCC) 100%Final finishes 54%

How to read construction stages

Compared with 6 similar projects in PIN 400072

Projects with 100–600 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400072
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths3 yrs 10 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Dec 2025 – Dec 2026Dec 2026
Concrete structure (RCC)100%100%
Units booked12%85%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pride Panorama by Landcare Realty LLP is a 274-unit BMC-sanctioned project in Chandivali, Mumbai 400072, registered with MahaRERA in 2 phases, with possession dates from December 2025 to December 2026. 34 units booked out of total 274 units. The concrete structure (RCC) is complete.

Read full summary

Pride Panorama is a BMC-sanctioned project by Landcare Realty LLP in Chandivali, Mumbai 400072, registered with MahaRERA as 2 phases (P51800034548, P51800048083). The first phase was launched in April 2022. Together the phases have 274 units in 6 buildings: 259 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from December 2025 to December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 54% complete. Both phases have their structure complete.

34 units booked out of total 274 units (12%).