ATTHIS at L and T Realty Elixir Reserve, Chandivali

by Larsen & Toubro Ltd. (Realty Division) · Chandivali, Mumbai 400072 · Map

Launched
Mar 20223 yrs 3 mths originally promised
Possession (MahaRERA)
Sep 2027Extended by 2 yrs 3 mths
Concrete structure
100%Nearing possession
Booked
165 of 19087%
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
142
3 BHK
48
Total units
190
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%165
100%100%80%165
100%100%80%165
100%0%0%165

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400072

Projects with 90–400 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400072
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths3 yrs 11 mths
Possession date extendedBy 2 yrs 3 mths1 of 5
Possession date (MahaRERA)Sep 2027Dec 2026
Concrete structure (RCC)100%100%
Units booked87%72%
MahaRERA complaints (filed by or against the builder)10

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

ATTHIS at L and T Realty Elixir Reserve by Larsen & Toubro Ltd. (Realty Division) (L&T Realty) is a 190-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in March 2022 with possession due in September 2027. 165 units booked out of total 190 units. The concrete structure (RCC) is complete.

Read full summary

ATTHIS at L and T Realty Elixir Reserve is a BMC-sanctioned project by Larsen & Toubro Ltd. (Realty Division) in Chandivali, Mumbai 400072, registered with MahaRERA as P51800033618. It was launched in March 2022. It has 190 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2027, extended by 2 years 3 months from the original June 2025. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

165 units booked out of total 190 units (87%).

L&T Realty's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA29
Total units across these projects4,949
Completed without extending the possession date11
Completed after an extension3
Lapsed3
Under construction12
Possession date extended on the builder's application8
Typical time from launch to 100% structure4 years 5 months
MahaRERA complaints (filed by or against the builder), all L&T Realty projects114 (16 of 29 projects)

See all L&T Realty projects →