Westwood, Kandivali West
by Dimple Realtors Private Limited · Kandivali West, Mumbai 400067 · Map
- Launched
- Apr 2022First of 2 phases
- Possession (MahaRERA)
- Dec 2027 – Dec 2030Not extended
- Concrete structure
- 61%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.5 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 249
- 2 BHK
- 227
- 3 BHK
- 1
- Other units
- 12
- Total units
- 489
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 2
- MahaRERA complaints
- 5
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Westwood Nearing possession | P51800034338 | 293 | 100% | 46% | |
| Westwood-2 Early stage | P51800045238 | 184 | 0% | – |
Show updates by phase
Westwood (P51800034338)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 24% | 139 | |
| 100% | 100% | 18% | 126 | |
| 100% | 100% | 0% | 114 | |
| 100% | 42% | 0% | 89 |
"–" means MahaRERA shows no figure for that update.
Westwood-2 (P51800045238)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400067
Projects with 200–1,000 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 2 mths | 3 yrs 7 mths |
| Possession date extended | No | 3 of 3 |
| Possession date (MahaRERA) | Dec 2027 – Dec 2030 | Mar 2027 |
| Concrete structure (RCC) | 61% | 100% |
| Units booked | – | 93% |
| MahaRERA complaints (filed by or against the builder) | 5 | 2 |
The 3 projects
- Castalia, Kandivali West
- Charkop Akash Kiran CHS Ltd, Kandivali West
- Veena Smart Homes, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Castalia | November 2021 | March 2027 | 100% | 287 units booked out of total 310 units |
| Charkop Akash Kiran CHS Ltd | September 2021 | April 2027 | 100% | 171 units booked out of 204 units for sale |
| Veena Smart Homes | May 2021 | Dec 2026 | 100% | 468 units booked out of total 503 units |
About this project
Westwood by Dimple Realtors Private Limited is a 489-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, registered with MahaRERA in 2 phases, with possession dates from December 2027 to December 2030. The concrete structure (RCC) is 61% complete.
Read full summary
Westwood is an SRA-sanctioned project by Dimple Realtors Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as 2 phases (P51800034338, P51800045238). The first phase was launched in April 2022. Together the phases have 489 units in 2 buildings: 477 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from December 2027 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 61% complete and final finishes 15% complete. Neither phase has its structure complete.