Skip to main content

Castalia, Kandivali West

by Triax Developers LLP · Kandivali West, Mumbai 400067 · Map

Launched
Nov 20214 yrs 1 mth originally promised
Possession (MahaRERA)
Mar 2027Extended by 1 yr 3 mths
Concrete structure
100%Nearing possession
Booked
287 of 31093%
Buildings
11.3 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
157
3 BHK
153
Total units
310
Buildings
1
Land
1.3 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services55%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 89%Dec 2025: Concrete structure (RCC) 96%Jul 2026: Concrete structure (RCC) 96%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 13%Dec 2025: Final finishes 26%Jul 2026: Final finishes 26%Oct 2026: Final finishes 55%Excavation 100%Concrete structure (RCC) 100%Final finishes 55%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%55%287
100%96%26%287
100%96%26%287
100%89%13%287

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400067

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 1 mth3 yrs 7 mths
Possession date extendedBy 1 yr 3 mths3 of 5
Possession date (MahaRERA)Mar 2027Dec 2026
Concrete structure (RCC)100%100%
Units booked93%90%
MahaRERA complaints (filed by or against the builder)31

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Castalia by Triax Developers LLP is a 310-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in November 2021 with possession due in March 2027. 287 units booked out of total 310 units. The concrete structure (RCC) is complete.

Read full summary

Castalia is an SRA-sanctioned project by Triax Developers LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800031613. It was launched in November 2021. It has 310 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, extended by 1 year 3 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 55% complete.

287 units booked out of total 310 units (93%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 96% to 100%.