Skip to main content

Agami Eternity, Bandra East

Ready to move

by Agami Spaces Private Limited · Bandra East, Mumbai 400051 · Map

Launched
Apr 20224 yrs 11 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
49 of 5098% · 16 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale49 booked out of 50 units

Rehab16 units for existing members

Total 66 units. Rehab units are not for sale.

Project facts

3 BHK
66
Total units
66
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
50
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 56%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 80%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%49
100%100%100%49
100%100%80%43
100%56%0%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400051

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400051
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths4 yrs 2 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Mar 2027Dec 2026
Concrete structure (RCC)100%100%
Units booked (free sale)98%100%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Agami Eternity by Agami Spaces Private Limited is a 66-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in April 2022 with possession due in March 2027. 49 units booked out of 50 units for sale. The concrete structure (RCC) is complete.

Read full summary

Agami Eternity is a MHADA-sanctioned project by Agami Spaces Private Limited in Bandra East, Mumbai 400051, registered with MahaRERA as P51800034339. It was launched in April 2022. It has 66 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 66 units, 50 are for sale and 16 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

49 units booked out of 50 units for sale (98%).