Rustomjee Aden, Bandra East
by Keysky Realtors Pvt Ltd · Bandra East, Mumbai 400051 · Map
- Launched
- Feb 20233 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 27 of 27100% · 42 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale27 booked out of 27 units
Rehab42 units for existing members
Total 69 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 13
- 3 BHK
- 53
- Other units
- 3
- Total units
- 69
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 27
- Rehab units
- 42
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 79% | 27 | |
| 100% | 100% | 35% | 27 | |
| 100% | 9% | 0% | 9 | |
| 100% | 9% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400051
Projects with 30–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 4 yrs 10 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Mar 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 100% | 98% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 3 projects
- Paranjape Athena, Bandra East
- Antariksh Ace, Bandra East
- Agami Eternity, Bandra East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Paranjape Athena | February 2023 | December 2027 | 100% | 6 units booked out of total 133 units |
| Antariksh Ace | September 2022 | December 2026 | 100% | 115 units booked out of total 115 units |
| Agami Eternity | April 2022 | March 2027 | 100% | 49 units booked out of 50 units for sale |
About this project
Rustomjee Aden by Keysky Realtors Pvt Ltd (Rustomjee) is a 69-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in February 2023 with possession due in December 2026. 27 units booked out of 27 units for sale. The concrete structure (RCC) is complete.
Read full summary
Rustomjee Aden is a MHADA-sanctioned project by Keysky Realtors Pvt Ltd in Bandra East, Mumbai 400051, registered with MahaRERA as P51800049222. It was launched in February 2023. It has 69 units in 1 building: 66 homes (2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 69 units, 27 are for sale and 42 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 79% complete.
27 units booked out of 27 units for sale (100%).
Rustomjee's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 38 |
|---|---|
| Total units across these projects | 3,435 |
| Completed without extending the possession date | 15 |
| Completed after an extension | 2 |
| Lapsed | 5 |
| Under construction | 16 |
| Possession date extended on the builder's application | 8 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Rustomjee projects | 119 (11 of 38 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.