Rajlaxmi Residency, Bandra East

Lapsed

by Raj Corporation · Bandra East, Mumbai 400051 · Map

Launched
Oct 20214 yrs 2 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked (free sale)
61 of 6890% · 58 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale61 booked out of 68 units

Rehab58 units for existing members

Land-owner share2 units, not for sale

Total 128 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
124
Other units
4
Total units
128
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
68
Rehab units
58
Land-owner share (not for sale)
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%61
100%0%0%–
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400051

Projects with 60–250 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400051
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths3 yrs 6 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Dec 2025Dec 2026
Concrete structure (RCC)0%100%
Units booked (free sale)90%94%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Rajlaxmi Residency by Raj Corporation is a 128-unit BMC-sanctioned project in Bandra East, Mumbai 400051, launched in October 2021; its MahaRERA registration has lapsed. 61 units booked out of 68 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Rajlaxmi Residency is a BMC-sanctioned project by Raj Corporation in Bandra East, Mumbai 400051, registered with MahaRERA as P51800031414. It was launched in October 2021. It has 128 units in 1 building: 124 homes (1 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 128 units, 68 are for sale, 58 are rehab units for existing members and 2 are the land-owner's share, not for sale.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

61 units booked out of 68 units for sale (90%).