Saraswati, Borivali West

Lapsed

by Karmvir Saraswati Developers LLP · Borivali West, Mumbai 400103 · Map

Launched
Apr 20222 yrs 8 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
20.9 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
44
2 BHK
67
3 BHK
28
Other units
19
Total units
159
Buildings
2
Land
0.9 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%–
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400103

Projects with 70–300 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400103
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths3 yrs
Possession date extendedNo2 of 3
Possession date (MahaRERA)Dec 2024Apr 2027
Concrete structure (RCC)0%100%
Units booked–41%
MahaRERA complaints (filed by or against the builder)40

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Saraswati by Karmvir Saraswati Developers LLP is a 159-unit project in Borivali West, Mumbai 400103, launched in April 2022; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Saraswati is a project by Karmvir Saraswati Developers LLP in Borivali West, Mumbai 400103, registered with MahaRERA as P51800034359. It was launched in April 2022. It has 159 units in 2 buildings: 140 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.