The Castle, Borivali West

by Solidago Realty · Borivali West, Mumbai 400103 · Map

Launched
Nov 20224 yrs 9 mths promised
Possession (MahaRERA)
Aug 2027Not extended
Concrete structure
98%Mid-construction
Booked (free sale)
42 of 10241% · 71 rehab units
Buildings
41 acre
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale42 booked out of 102 units

Rehab71 units for existing members

Total 173 units. Rehab units are not for sale.

Project facts

1 BHK
26
2 BHK
79
3 BHK
46
Other units
22
Total units
173
Buildings
4
Land
1 acre
Phases
1
MahaRERA complaints
0
Free-sale units
102
Rehab units
71

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)98%
Finishes, lifts and services72%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 98%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 72%Excavation 100%Concrete structure (RCC) 98%Final finishes 72%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%72%42
95%90%0%39
95%90%0%–
95%85%0%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400103

Projects with 70–350 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400103
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 9 mths3 yrs
Possession date extendedNo1 of 3
Possession date (MahaRERA)Aug 2027Mar 2027
Concrete structure (RCC)98%100%
MahaRERA complaints (filed by or against the builder)01

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

The Castle by Solidago Realty is a 173-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in November 2022 with possession due in August 2027. 42 units booked out of 102 units for sale. The concrete structure (RCC) is 98% complete.

Read full summary

The Castle is a BMC-sanctioned project by Solidago Realty in Borivali West, Mumbai 400103, registered with MahaRERA as P51800047865. It was launched in November 2022. It has 173 units in 4 buildings: 151 homes (1, 2 and 3 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 173 units, 102 are for sale and 71 are rehab units for existing members.

Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 98% complete, final finishes 72% complete.

42 units booked out of 102 units for sale (41%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 90% to 98%.