Shiv Lilam, Dahisar

Lapsed

by Navkarmik Infra & Development Private Limited · Dahisar, Mumbai 400068 · Map

Launched
Apr 20222 yrs 11 mths promised
Possession (MahaRERA)
Mar 2025Not extendedWhat does Lapsed mean?
Concrete structure
86%Mid-construction
Booked
49 of 5196%
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
22
2 BHK
24
Other units
5
Total units
51
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)86%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 86%Dec 2025: Concrete structure (RCC) 86%Jul 2026: Concrete structure (RCC) 86%Oct 2026: Concrete structure (RCC) 86%Dec 2024: Final finishes 30%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 86%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%86%30%49
100%86%30%–
100%86%30%–
100%86%30%49

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400068

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths3 yrs 6 mths
Possession date extendedNo2 of 5
Possession date (MahaRERA)Mar 2025Jun 2026
Concrete structure (RCC)86%100%
Units booked96%42%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Shiv Lilam by Navkarmik Infra & Development Private Limited is a 51-unit project in Dahisar, Mumbai 400068, launched in April 2022; its MahaRERA registration has lapsed. 49 units booked out of total 51 units. The concrete structure (RCC) is 86% complete.

Read full summary

Shiv Lilam is a project by Navkarmik Infra & Development Private Limited in Dahisar, Mumbai 400068, registered with MahaRERA as P51800034980. It was launched in April 2022. It has 51 units in 1 building: 46 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 86% complete, final finishes 30% complete.

49 units booked out of total 51 units (96%).