Vivan, Goregaon West
by Goregaon Electrical Industries LLP · Goregaon West, Mumbai 400104 · Map
- Launched
- Apr 20226 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 20%Mid-construction
- Booked
- 160 of 40739%
- Buildings
- 51.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 321
- 2 BHK
- 84
- Other units
- 2
- Total units
- 407
- Buildings
- 5
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 20% | 20% | 160 | |
| 100% | 20% | 20% | 160 | |
| 100% | 20% | 20% | – | |
| 100% | 20% | 19% | 69 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400104
Projects with 200–900 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 8 mths | 4 yrs |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Dec 2028 | Nov 2026 |
| Concrete structure (RCC) | 20% | 74% |
| Units booked | 39% | 78% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Integrated Ramicon, Goregaon West
- Sushanku Avenue, Goregaon West
- Sejal Kajal Apartment Chs Ltd, Goregaon West
- Asmi Legacy, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Integrated Ramicon | June 2022 | Dec 2026 – Dec 2027 | 97% | 378 units booked out of 398 units for sale |
| Sushanku Avenue | June 2022 | Nov 2026 – Dec 2027 | 100% | 320 units booked out of 352 units for sale |
| Sejal Kajal Apartment Chs Ltd | August 2022 | July 2026 | 33% | 91 units booked out of 139 units for sale |
| Asmi Legacy | November 2021 | December 2026 | 51% | 70 units booked out of 190 units for sale |
About this project
Vivan by Goregaon Electrical Industries LLP is a 407-unit SRA-sanctioned project in Goregaon West, Mumbai 400104, launched in April 2022 with possession due in December 2028. 160 units booked out of total 407 units. The concrete structure (RCC) is 20% complete.
Read full summary
Vivan is an SRA-sanctioned project by Goregaon Electrical Industries LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800035019. It was launched in April 2022. It has 407 units in 5 buildings: 405 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes 20% complete.
160 units booked out of total 407 units (39%).