Sushanku Avenue, Goregaon West
Ready to move
by Sushanku Realty Private Limited · Goregaon West, Mumbai 400104 · Map
- Launched
- Jun 2022First of 2 phases
- Possession (MahaRERA)
- Nov 2026 – Dec 2027Extended in 1 of 2 phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked (free sale)
- 320 of 35291% · 159 rehab units
- Buildings
- 30.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale320 booked out of 352 units
Rehab159 units for existing members
Total 511 units. Rehab units are not for sale.
Project facts
- 1 RK
- 7
- 1 BHK
- 253
- 2 BHK
- 244
- 3 BHK
- 1
- Other units
- 6
- Total units
- 511
- Buildings
- 3
- Land
- 0.6 acres
- Phases
- 2
- MahaRERA complaints
- 0
- Free-sale units
- 352
- Rehab units
- 159
- Reserved units
- 34
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Sushanku Avenue 36 Ready to move | P51800046272 | 273 | 100% | 70% | |
| Sushanku Avenue 37 Ready to move | P51800077600 | 232 | 100% | 54% |
Show updates by phase
Sushanku Avenue 36 (P51800046272)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 194 | |
| 100% | 100% | 100% | 194 | |
| 100% | 90% | 0% | 189 | |
| 100% | 90% | 0% | 30 |
"–" means MahaRERA shows no figure for that update.
Sushanku Avenue 37 (P51800077600)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 126 | |
| 100% | 95% | 40% | 98 | |
| 100% | 60% | 0% | 44 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400104
Projects with 250–1,100 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 4 mths | 5 yrs 1 mth |
| Possession date extended | Yes | 0 of 3 |
| Possession date (MahaRERA) | Nov 2026 – Dec 2027 | Dec 2026 |
| Concrete structure (RCC) | 100% | 51% |
| Units booked (free sale) | 91% | 39% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Integrated Ramicon, Goregaon West
- Vivan, Goregaon West
- Asmi Legacy, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Integrated Ramicon | June 2022 | Dec 2026 – Dec 2027 | 97% | 378 units booked out of 398 units for sale |
| Vivan | April 2022 | December 2028 | 20% | 160 units booked out of total 407 units |
| Asmi Legacy | November 2021 | December 2026 | 51% | 70 units booked out of 190 units for sale |
About this project
Sushanku Avenue by Sushanku Realty Private Limited is a 511-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, registered with MahaRERA in 2 phases, with possession dates from November 2026 to December 2027. 320 units booked out of 352 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sushanku Avenue is a MHADA-sanctioned project by Sushanku Realty Private Limited in Goregaon West, Mumbai 400104, registered with MahaRERA as 2 phases (P51800046272, P51800077600). The first phase was launched in June 2022. Together the phases have 511 units in 3 buildings: 505 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA. Of the 511 units, 352 are for sale and 159 are rehab units for existing members.
The phases' registered possession dates run from November 2026 to December 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 95% complete. Both phases have their structure complete.
320 units booked out of 352 units for sale (91%). Since the July 2026 update, 28 more units have been booked.