Skip to main content

Asmi Legacy, Goregaon West

by Asmi Developers · Goregaon West, Mumbai 400104 · Map

Launched
Nov 20215 yrs 1 mth promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
51%Mid-construction
Booked (free sale)
70 of 19037% · 76 rehab units
Buildings
20.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale70 booked out of 190 units

Rehab76 units for existing members

Total 266 units. Rehab units are not for sale.

Project facts

1 BHK
52
2 BHK
168
3 BHK
46
Total units
266
Buildings
2
Land
0.9 acres
Phases
1
MahaRERA complaints
0
Free-sale units
190
Rehab units
76

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)51%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 6%Jul 2026: Concrete structure (RCC) 39%Oct 2026: Concrete structure (RCC) 51%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 51%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%51%0%70
100%39%0%73
100%6%0%53
100%0%0%28

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400104

Projects with 100–600 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400104
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 1 mth3 yrs 8 mths
Possession date extendedNo2 of 4
Possession date (MahaRERA)Dec 2026Jun 2027
Concrete structure (RCC)51%97%
Units booked (free sale)37%77%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Asmi Legacy by Asmi Developers is a 266-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in November 2021 with possession due in December 2026. 70 units booked out of 190 units for sale. The concrete structure (RCC) is 51% complete.

Read full summary

Asmi Legacy is a MHADA-sanctioned project by Asmi Developers in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800031746. It was launched in November 2021. It has 266 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 266 units, 190 are for sale and 76 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 51% complete, final finishes not started.

70 units booked out of 190 units for sale (37%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 39% to 51%.