Skip to main content

Charkop Gitanjali Co Op Housing Society Limited, Kandivali West

Ready to move

by Charkop Gitanjali Co-Op Housing Society Limited · Kandivali West, Mumbai 400067 · Map

Launched
May 20223 yrs originally promised
Possession (MahaRERA)
Apr 2027Extended by 1 yr 11 mths
Concrete structure
100%Ready to move
Booked (free sale)
32 of 32100% · 21 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale32 booked out of 32 units

Rehab21 units for existing members

Total 53 units. Rehab units are not for sale.

Project facts

1 BHK
4
2 BHK
34
3 BHK
15
Total units
53
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
32
Rehab units
21

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 98%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 20%Dec 2025: Final finishes 98%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%32
100%100%100%32
100%100%98%32
100%98%20%21

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs
Possession date extendedBy 1 yr 11 mths2 of 6
Possession date (MahaRERA)Apr 2027Aug 2026
Concrete structure (RCC)100%100%
Units booked (free sale)100%80%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Charkop Gitanjali Co Op Housing Society Limited by Charkop Gitanjali Co-Op Housing Society Limited is a 53-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in May 2022 with possession due in April 2027. 32 units booked out of 32 units for sale. The concrete structure (RCC) is complete.

Read full summary

Charkop Gitanjali Co Op Housing Society Limited is a MHADA-sanctioned project by Charkop Gitanjali Co-Op Housing Society Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800045647. It was launched in May 2022. It has 53 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 53 units, 32 are for sale and 21 are rehab units for existing members.

Its registered possession date is April 2027, extended by 1 year 11 months from the original May 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

32 units booked out of 32 units for sale (100%).