Jade Chsl, Kandivali West
by Shree Mahavir Constructions · Kandivali West, Mumbai 400067 · Map
- Launched
- Jun 20227 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 85%Mid-construction
- Booked (free sale)
- 10 of 2148% · 26 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 21 units
Rehab26 units for existing members
Total 47 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 22
- 3 BHK
- 22
- 4 BHK
- 1
- Other units
- 2
- Total units
- 47
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 21
- Rehab units
- 26
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 45% | 10 | |
| 100% | 85% | 40% | 5 | |
| 100% | 80% | 0% | 3 | |
| 100% | 65% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 6 mths | 3 yrs 1 mth |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Nov 2026 |
| Concrete structure (RCC) | 85% | 100% |
| Units booked (free sale) | 48% | 90% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Charkop Siddhiyog Co Operative Housing Society Limited, Kandivali West
- Charkop Priyanka Cooperative Housing Society Limited, Kandivali West
- X Line Shraddha Apartment, Kandivali West
- Charkop Gitanjali Co Op Housing Society Limited, Kandivali West
- Shree Vrindavan, Kandivali West
- Self Redevelopment Of Charkop Shalimar Chs Ltd, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Charkop Siddhiyog Co Operative Housing Society Limited | June 2022 | December 2025 | 95% | 45 units booked out of total 55 units |
| Charkop Priyanka Cooperative Housing Society Limited | June 2022 | October 2026 | 100% | 43 units booked out of 55 units for sale |
| X Line Shraddha Apartment | May 2022 | December 2024 | 100% | 24 units booked out of 24 units for sale |
| Charkop Gitanjali Co Op Housing Society Limited | May 2022 | April 2027 | 100% | 32 units booked out of 32 units for sale |
| Shree Vrindavan | March 2022 | June 2027 | 93% | 29 units booked out of 42 units for sale |
| Self Redevelopment Of Charkop Shalimar Chs Ltd | October 2022 | December 2026 | 100% | 37 units booked out of 38 units for sale |
About this project
Jade Chsl by Shree Mahavir Constructions is a 47-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in June 2022 with possession due in December 2029. 10 units booked out of 21 units for sale. The concrete structure (RCC) is 85% complete.
Read full summary
Jade Chsl is a BMC-sanctioned project by Shree Mahavir Constructions in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800046042. It was launched in June 2022. It has 47 units in 2 buildings: 45 homes (2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 21 are for sale and 26 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes 45% complete.
10 units booked out of 21 units for sale (48%). Since the July 2026 update, 5 more units have been booked.