Skip to main content

Jade Chsl, Kandivali West

by Shree Mahavir Constructions · Kandivali West, Mumbai 400067 · Map

Launched
Jun 20227 yrs 6 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
85%Mid-construction
Booked (free sale)
10 of 2148% · 26 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 21 units

Rehab26 units for existing members

Total 47 units. Rehab units are not for sale.

Project facts

2 BHK
22
3 BHK
22
4 BHK
1
Other units
2
Total units
47
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
21
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services45%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 65%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 40%Oct 2026: Final finishes 45%Excavation 100%Concrete structure (RCC) 85%Final finishes 45%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%45%10
100%85%40%5
100%80%0%3
100%65%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 6 mths3 yrs 1 mth
Possession date extendedNo3 of 6
Possession date (MahaRERA)Dec 2029Nov 2026
Concrete structure (RCC)85%100%
Units booked (free sale)48%90%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Jade Chsl by Shree Mahavir Constructions is a 47-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in June 2022 with possession due in December 2029. 10 units booked out of 21 units for sale. The concrete structure (RCC) is 85% complete.

Read full summary

Jade Chsl is a BMC-sanctioned project by Shree Mahavir Constructions in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800046042. It was launched in June 2022. It has 47 units in 2 buildings: 45 homes (2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 21 are for sale and 26 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes 45% complete.

10 units booked out of 21 units for sale (48%). Since the July 2026 update, 5 more units have been booked.