Sheetal Anupam, Malad West
Ready to moveLapsed
by Dgs Township Pvt Ltd · Malad West, Mumbai 400064 · Map
- Launched
- Jun 20222 yrs 11 mths promised
- Possession (MahaRERA)
- May 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 25 of 2696% · 34 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale25 booked out of 26 units
Rehab34 units for existing members
Total 60 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 3
- 2 BHK
- 32
- 3 BHK
- 14
- Other units
- 10
- Total units
- 60
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 26
- Rehab units
- 34
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 25 | |
| 100% | 100% | 90% | 25 | |
| 100% | 100% | 90% | 25 | |
| 100% | 93% | 10% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400064
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs 2 mths |
| Possession date extended | No | 3 of 4 |
| Possession date (MahaRERA) | May 2025 | Oct 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 96% | 97% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 4 projects
- Malad Sati Darshan CHS Ltd, Malad West
- Siddha Shila, Malad West
- Rite Amor, Malad West
- Ramdev Veeral Heights, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Malad Sati Darshan CHS Ltd | June 2022 | January 2027 | 100% | 34 units booked out of 35 units for sale |
| Siddha Shila | June 2022 | December 2025 | 60% | 99 units booked out of total 99 units |
| Rite Amor | April 2022 | December 2026 | 100% | 42 units booked out of 43 units for sale |
| Ramdev Veeral Heights | September 2022 | August 2026 | 100% | 2 units booked out of 28 units for sale |
About this project
Sheetal Anupam by Dgs Township Pvt Ltd is a 60-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in June 2022; its MahaRERA registration has lapsed. 25 units booked out of 26 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sheetal Anupam is a BMC-sanctioned project by Dgs Township Pvt Ltd in Malad West, Mumbai 400064, registered with MahaRERA as P51800046247. It was launched in June 2022. It has 60 units in 1 building: 50 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 60 units, 26 are for sale and 34 are rehab units for existing members.
Possession was due in May 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
25 units booked out of 26 units for sale (96%).