Leo Eminence, Bandra East

by Leo Infrastructure Private Limited · Bandra East, Mumbai 400051 · Map

Launched
Jun 20223 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Nearing possession
Booked
127 of 15582% · 123 in Jul 2026
Buildings
30.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
43
2 BHK
111
Total units
155
Buildings
3
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 11%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 5%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%127
100%100%50%123
100%70%5%41
100%11%0%58

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400051

Projects with 70–350 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400051
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths4 yrs 2 mths
Possession date extendedBy 1 yr0 of 4
Possession date (MahaRERA)Dec 2026Jun 2026
Concrete structure (RCC)100%98%
Units booked82%92%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Leo Eminence by Leo Infrastructure Private Limited is a 155-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in June 2022 with possession due in December 2026. 127 units booked out of total 155 units. The concrete structure (RCC) is complete.

Read full summary

Leo Eminence is a MHADA-sanctioned project by Leo Infrastructure Private Limited in Bandra East, Mumbai 400051, registered with MahaRERA as P51800046335. It was launched in June 2022. It has 155 units in 3 buildings, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

127 units booked out of total 155 units (82%). Since the July 2026 update, 4 more units have been booked.