Bc Corp Arista, Bandra East

Lapsed

by Tristar Development LLP · Bandra East, Mumbai 400051 · Map

Launched
Aug 20223 yrs 4 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
95%Mid-construction
Booked (free sale)
91 of 9794% · 54 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale91 booked out of 97 units

Rehab54 units for existing members

Total 151 units. Rehab units are not for sale.

Project facts

2 BHK
135
3 BHK
16
Total units
151
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
97
Rehab units
54

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 18%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 95%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%91
100%95%0%91
100%95%0%91
100%18%0%53

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400051

Projects with 70–350 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400051
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths4 yrs 2 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Dec 2025Dec 2026
Concrete structure (RCC)95%100%
Units booked (free sale)94%86%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Bc Corp Arista by Tristar Development LLP is a 151-unit BMC-sanctioned project in Bandra East, Mumbai 400051, launched in August 2022; its MahaRERA registration has lapsed. 91 units booked out of 97 units for sale. The concrete structure (RCC) is 95% complete.

Read full summary

Bc Corp Arista is a BMC-sanctioned project by Tristar Development LLP in Bandra East, Mumbai 400051, registered with MahaRERA as P51800046486. It was launched in August 2022. It has 151 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 151 units, 97 are for sale and 54 are rehab units for existing members.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.

91 units booked out of 97 units for sale (94%).