- Launched
- Aug 20222 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jun 2025Extended by 6 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 63 of 6597% · 21 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale63 booked out of 65 units
Rehab21 units for existing members
Total 86 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 41
- 2 BHK
- 27
- 3 BHK
- 18
- Total units
- 86
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 65
- Rehab units
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 63 | |
| 100% | 100% | 98% | – | |
| 100% | 100% | 100% | 46 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400104
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 4 mths | 3 yrs 8 mths |
| Possession date extended | By 6 mths | 0 of 4 |
| Possession date (MahaRERA) | Jun 2025 | Nov 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 97% | 82% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Siddharth Nagar Paradise Chs Ltd, Goregaon West
- Hitendra Dhamm Shabha Co-operative Housing Society Limited, Goregaon West
- Siddharth Nagar Siddhivinayak Chs Ltd, Goregaon West
- Siddharth Nagar Goodwill Chsl, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Siddharth Nagar Paradise Chs Ltd | February 2023 | December 2026 | 100% | 48 units booked out of 60 units for sale |
| Hitendra Dhamm Shabha Co-operative Housing Society Limited | February 2023 | September 2026 | 100% | 47 units booked out of 56 units for sale |
| Siddharth Nagar Siddhivinayak Chs Ltd | February 2023 | December 2027 | 100% | 47 units booked out of 54 units for sale |
| Siddharth Nagar Goodwill Chsl | February 2023 | December 2025 | 100% | 27 units booked out of total 65 units |
About this project
Odc 1 by NVN Buildcon LLP is an 86-unit MMRDA-sanctioned project in Goregaon West, Mumbai 400104, launched in August 2022 with possession due in June 2025. 63 units booked out of 65 units for sale. The concrete structure (RCC) is complete.
Read full summary
Odc 1 is an MMRDA-sanctioned project by NVN Buildcon LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800046544. It was launched in August 2022. It has 86 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 86 units, 65 are for sale and 21 are rehab units for existing members.
Possession was due in June 2025, after an extension of 6 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
63 units booked out of 65 units for sale (97%).