Siddharth Nagar Paradise Chs Ltd, Goregaon West

Ready to move

by Infinity Constructions · Goregaon West, Mumbai 400104 · Map

Launched
Feb 20233 yrs 10 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked (free sale)
48 of 6080% · 18 rehab units
Buildings
11.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale48 booked out of 60 units

Rehab18 units for existing members

Total 78 units. Rehab units are not for sale.

Project facts

1 BHK
19
2 BHK
39
3 BHK
19
Other units
1
Total units
78
Buildings
1
Land
1.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
60
Rehab units
18

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 99%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 4%Dec 2025: Final finishes 4%Jul 2026: Final finishes 49%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%48
50%50%49%48
50%50%4%45
100%99%4%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400104

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400104
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths3 yrs 1 mth
Possession date extendedNo2 of 6
Possession date (MahaRERA)Dec 2026Sep 2026
Concrete structure (RCC)100%100%
Units booked (free sale)80%84%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Siddharth Nagar Paradise Chs Ltd by Infinity Constructions is a 78-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in February 2023 with possession due in December 2026. 48 units booked out of 60 units for sale. The concrete structure (RCC) is complete.

Read full summary

Siddharth Nagar Paradise Chs Ltd is a MHADA-sanctioned project by Infinity Constructions in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800049649. It was launched in February 2023. It has 78 units in 1 building: 77 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 78 units, 60 are for sale and 18 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

48 units booked out of 60 units for sale (80%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 50% to 100%.