Siddharth Nagar Goodwill Chsl, Goregaon West
Lapsed
by Virendra Hiralal Doshi · Goregaon West, Mumbai 400104 · Map
- Launched
- Feb 20232 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 27 of 6542%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 51
- 3 BHK
- 14
- Total units
- 65
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 27 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 60% | 0% | 27 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400104
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 6 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | Dec 2025 | Sep 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 42% | 87% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Siddharth Nagar Siddhivinayak Chs Ltd, Goregaon West
- Hitendra Dhamm Shabha Co-operative Housing Society Limited, Goregaon West
- Siddharth Nagar Paradise Chs Ltd, Goregaon West
- Luxury Chsl Ltd, Goregaon West
- Atria Arshabharat, Goregaon West
- Odc 1, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Siddharth Nagar Siddhivinayak Chs Ltd | February 2023 | December 2027 | 100% | 47 units booked out of 54 units for sale |
| Hitendra Dhamm Shabha Co-operative Housing Society Limited | February 2023 | September 2026 | 100% | 47 units booked out of 56 units for sale |
| Siddharth Nagar Paradise Chs Ltd | February 2023 | December 2026 | 100% | 48 units booked out of 60 units for sale |
| Luxury Chsl Ltd | April 2023 | September 2026 | 100% | 57 units booked out of 57 units for sale |
| Atria Arshabharat | April 2023 | August 2026 | 80% | – |
| Odc 1 | August 2022 | June 2025 | 100% | 63 units booked out of 65 units for sale |
About this project
Siddharth Nagar Goodwill Chsl by Virendra Hiralal Doshi is a 65-unit project in Goregaon West, Mumbai 400104, launched in February 2023; its MahaRERA registration has lapsed. 27 units booked out of total 65 units. The concrete structure (RCC) is complete.
Read full summary
Siddharth Nagar Goodwill Chsl is a project by Virendra Hiralal Doshi in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800049418. It was launched in February 2023. It has 65 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.
27 units booked out of total 65 units (42%).